Event Summary |
FILE SAVED AS: MISO_23899_20180529_1215.htm
|
Incident:
|
MISO_23899_20180529_1215
|
Date: 05/29/2018 (CST)
|
Reliability Coordinator: MISO
|
Initial Conditions:
|
N/A
|
Flowgate:
|
23899 - Clifty Creek-Buffington 138kV ...
|
Rating: 0
|
LODF: 15.45%
|
TLR Direction:
|
Normal
|
Effective StartTime:
|
05/29/2018 12:15 (CST)
|
Effective EndTime: 05/29/2018 19:00 (CST)
|
TLR Duration: 6 Hours and 45 Minutes
|
|
TLR Actions |
May 29
11:54 (CST)
|
TLR 5A
|
NEXT
|
NONE
|
|
|
|
NONE
|
0
|
0
|
0
|
May 29
12:29 (CST)
|
TLR 5A
|
NEXT
|
|
|
|
|
|
|
|
|
|
|
|
NONE
|
0
|
0
|
0
|
May 29
13:27 (CST)
|
TLR 5A
|
NEXT
|
|
|
|
|
|
|
|
|
|
|
|
NONE
|
0
|
0
|
0
|
May 29
14:32 (CST)
|
TLR 5A
|
NEXT
|
|
|
|
|
|
|
|
|
|
|
|
NONE
|
0
|
0
|
0
|
May 29
15:43 (CST)
|
TLR 5A
|
NEXT
|
|
|
|
|
|
|
|
|
|
|
|
NONE
|
0
|
0
|
0
|
May 29
16:44 (CST)
|
TLR 1
|
CURRENT
|
NONE
|
NONE
|
NONE
|
0
|
0
|
0
|
May 29
18:30 (CST)
|
TLR 0
|
CURRENT
|
NONE
|
NONE
|
NONE
|
0
|
0
|
0
|
|
|
|
TLR Schedule Totals |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
2 |
0 |
0 |
0 |
0 |
3 |
0 |
0 |
0 |
0 |
4 |
0 |
0 |
0 |
0 |
5 |
0 |
0 |
0 |
0 |
6 |
0 |
0 |
0 |
0 |
7 |
23 |
177 |
177 |
0 |
Total |
23 |
177 |
177 |
0 |
|
|
|
TLR NNL Totals |
CIN |
6.0 |
7.0 |
LGEE |
67.0 |
67.0 |
PJM |
956.0 |
957.0 |
Total |
1029.0 |
1031.0 |
|
|
|